
|
Updates as of 6/25/08 Bishop Carroll Building Project Continues Upward The new gym and classroom space at Bishop Carroll Catholic High School shows progress every day. Pictured are both parts of the Building The Tradition Capital Campaign projects:
* Viewing from the southeast section of the campus, the two-story shell for thirteen classrooms (5 science labs and 8 regular classrooms) is being added on to the south of the existing academic hallways.
Updates as of 6/12/08
The pouring of the hall floors.
Updates as of 5/27/08 Bishop Carroll Construction on Schedule! Phase I of our Building The Tradition building project began last November, and construction is right on schedule. The huge hole excavated is being filled with concrete walls, pillars, and concrete block separating the locker room, office, and shower spaces. Backfilling proceeds as we go to press, using the dirt pile on the front lawn! Chris Baalmann 01, the project engineer for Simpson & Associates, projects that the activities center will be completed next spring, barring unforeseen bad weather. The shell for 13 additional classrooms is visible atop the concrete floor which projects south from the existing academic halls. Five science labs and 8 regular classrooms will be finished in Phase I. The entire project is funded by the Building The Tradition Capital Campaign which continues in its “silent phase” of donor cultivation. The campaign has raised $10.3 million in pledges, with $17.5 million needed for the entire building and renovation project that includes expanded commons and new auditorium. The development department continues to work towards that goal.
The north wall of BCCHS's new gym is built higher. Bleachers to seat up to 2000 will be installed around the "sunken" court.
Updates as of 05/9/08 The west wall of Bishop
Carroll's new gym shows where the bleachers will be built upon the
concrete columns.
Updates as of 04/29/08
More Updates!!! Construction continues on the activities center and classroom addition at Bishop Carroll High School. Pictured (first picture) is the area where the east bleachers will go in the gymnasium and (second picture) where the walls will go up on the classroom shell! The general contracting company is Simpson & Associates, and BC alum Chris Baalman '01 is the project engineer. With favorable weather, the gym will be complete next spring!
Updates as of 04/02/08 Bishop Carroll's Building Project Progresses!! Construction continues on the new activities complex at Bishop Carroll with the gym walls erected and waterproofed. In addition, the footprint for the thirteen more classrooms is complete with the footings and preliminary plumbing visible. The "big dirt pile" in the front yard eventually will be used for fill-in and additional landscaping. To date, $10.12 million has been raised for the entire Building The Tradition Capital Campaign from within the BC community, but another $7 million is needed to enlarge the chapel, expand the commons and kitchen, and build a new auditorium.
Updates as of 03/07/08 Foundation is being laid for the new gym.
Updates as of 01/11/08 What's with the big dirt pile in front of Bishop Carroll?
Construction has begun on the new gym at Carroll, and the dirt is from the hole which was dug for it. Workers are preparing the area with required drainage and other necessary steps prior to main construction. Work also is happening to prepare where the classroom addition at the south end of the existing academic halls is planned. The foyer and gym will be entered at ground level, and spectators will walk down to their seats. The original "concrete cave" will remain as our secondary gym, since the little "girl's gym" will be remodeled as classroom, storage and practice space for the band. To date $9.3 million in pledges have been raised within the Bishop Carroll community to make this happen! The Building The Tradition capital campaign continues in its "silent phase" with personal visits by BC volunteers.
Updates as of 11/30/07 Complex Groundbreaking November 28
Groundbreaking ceremonies
for the Bishop Carroll Catholic High School Activities Complex were held
at 1:30 pm on Wednesday, November 28.
Bishop Michael Jackels, President Leticia Nielsen, contractor Bob
Simpson of Simpson and Associates, athletic/activities director Larry
Dostert, architects Joe Johnson, Kenton Cox, Shannon Bohm and Kathy
Spencer of Schaefer Johnson Cox Frey, Campaign Chairs Jim McAnarney and
Pat Burns, Honorary Campaign Chairs Chris and Becky Dugan, Larry and Dana
Fugate, Alvin and Karla Neville; School Council Chair Gretchen Sharp,
Chaplain C. Jarrod Lies, faculty and staff, BCCHS students, and other
distinguished guests attended. The complex will seat 2000 with room to expand to 2500 and include new locker facilities for boys and girls physical education classes, athletic teams and activities. The $8 million project is funded by gifts from the BCCHS community and is expected to be constructed in 460 working days, to be completed during the 2009-2010 school year.
Update as of 7/10/07! Work continues on the renovation of the soccer and parking facilities at Bishop Carroll Catholic High School. South of the school building, the soccer field has been realigned to the north and south, and earth work continues in the parking lot and construction staging areas. The grassy space is cleared for work to
begin.
Drainage lines are laid in the trench.
Update as of 3/14/07! Demolition of the Convent
|